i3Dnet - [Network Maintenance] Aggregation Switch Upgrade - Sao Paulo – October 8, 2026 - MCOM-475 – Détails de la maintenance

Performances partiellement dégradées

OCT8

[Network Maintenance] Aggregation Switch Upgrade - Sao Paulo – October 8, 2026 - MCOM-475

Planifiéeoctobre 08, 2026 à 12:00 – 16:00UTC

Affecte

Datacenters

En maintenance depuis 12:00 PM à 12:00 AM

São Paulo - brcoa1

En maintenance depuis 12:00 PM à 12:00 AM

Mises à jour
  • Planifiée
    septembre 20, 2026 à 03:32UTC
    Planifiée
    septembre 20, 2026 à 03:32UTC

    We would like to notify you of upcoming network maintenance activities that will affect services in our São Paulo datacenter. The network maintenance has been scheduled for October 8, 2026.

    Location
    São Paulo, Brazil

    Schedule
    Start time: October 8, 2026, 08:00 UTC
    End time: October 8, 2026, 12:00 UTC

    Reason for this maintenance
    We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

    Expected impact
    Reduced redundancy: No impact is expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.