Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Power Maintenance] Busbar Replacement - Rotterdam – March 31, 2026

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for March 31, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: March 31, 2026, 05:00 UTC End time: March 31, 2026, 16:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to address a faulty busbar. This critical replacement will enhance system reliability and ensure consistent performance moving forward.

Expected impact: Reduced redundancy: No impact expected but there will be no UPS backup. To ensure there is no impact we will run the generators in sync with the grid.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Router Software Upgrade - Oslo - April 1, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Oslo datacenter. The network maintenance has been scheduled for April 1, 2026.

Location: Oslo, Norway

Schedule: Start time: April 1, 2026, 04:00 UTC End time: April 1, 2026, 07:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our router(s) to improve quality and ensure long-term reliability.

Expected impact: No Impact: No impact is expected for this maintenance, as the traffic will be routed via alternate paths.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Infrastructure Maintenance] Load Balancer and Database update - Global - April 22, 2026

Dear Client,

We would like to notify you of upcoming infrastructure maintenance activities that will affect services globally. The maintenance has been scheduled for April 22, 2026.

Location: Global

Schedule: Start time: April 22, 2026, 10:00 UTC End time: April 22, 2026, 11:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance: We will be performing updates on our database to improve quality and ensure long-term reliability.

Expected impact: Service degradation: During the maintenance all users will be disconnected while the switchover is performed. Calls to the API will briefly fail during the switchover.

Affected services: ONE portal: users will be logged out Smartdc portal: users will be logged out ODP: hostagents connection will be reset API: during the switchover calls will fail

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Power Maintenance] Breaker Maintenance Powerhouse 1 - Rotterdam – April 29

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for April 29, 2026

Location: Rotterdam, The Netherlands Suite 2 A Feed Suite 19 A and A+ Feed Suite 34 A and A+ Feed

Schedule: Start time: April 29, 2026, 08:00 UTC End time: April 29, 2026, 12:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance: Mandatory maintenance to ensure the safety, reliability and correct operation of our main power infrastructure.

Expected impact: Reduced redundancy: During the maintenance window, one of the power feeds supplying Suite 2, 19 and 34 will be temporarily unavailable. Power will remain available through the remaining feed(s), but power redundancy will be reduced for approximately 4 hours.

Please note that devices with a single power supply (single PSU) or devices connected only to the A feed will experience a service interruption during this maintenance window. Devices with dual power supplies connected to separate feeds are expected to remain online.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: i3d.net/support

[Cooling Maintenance] Water Cooling Pump Maintenance - Rotterdam – May 4, 2026

Dear Client,

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The water cooling pump maintenance has been scheduled for May 4, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: May 4, 2026, 07:00 UTC End time: May 4, 2026, 15:30 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: Our vendor will be performing a maintenance on the water pumps in our Rotterdam datacenter.

Expected impact: No Impact: No impact is expected, as maintenance activities will be performed on each water pump individually, with the team waiting for each pump to return to operation before proceeding to the next.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Generator On-load Test - Rotterdam – May 5, 2026

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for May 5, 2026

Location: Rotterdam, The Netherlands

Original window: Start time: May 5, 2026, 06:00 UTC End time: May 5, 2026, 09:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: To ensure the proper functioning of our power infrastructure, our generators will undergo an on-load test run.

Expected impact: No Impact: No impact is expected for this maintenance, as there is no outage for the power systems. Customers in the datacenter at the time of the maintenance can hear loud noises.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

Past Incidents

Friday 22nd, July 2022

HK: Hong Kong Backbone link between our Hong Kong and Tokyo datacenters

At this moment we are experiencing problems with: Backbone link between our Hong Kong and Tokyo datacenters down.

The cause of the incident is currently: Unknown

We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

Estimated time of repair: Unknown.

Impact: Due to the current incident on our backbone link between our Hong Kong and Tokyo datacenters, users between these and surrounding regions may experience increased latency.

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident was caused by a planned maintenance where a line card was replaced. Unfortunately the new line card did not work as expected causing the circuit to stay down after the maintenance window ended. Vendor has reverted the change where after the link restored and doing traffic again.

  • Thursday 21st, July 2022

    DE: Frankfurt Backbone link between our Frankfurt and Vienna datacenters down

    At this moment we are experiencing problems with: Backbone link between our Frankfurt and Vienna datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Frankfurt and Vienna datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. Fiber cut is repaired and vendor hands-off

  • Repair crew is onsite and started cable preparation works. ETR currently unknown.

  • The cause was identified by the vendor. A fiber cut was found due to excavation works. Vendor reported a ETA of 6am UTC for the fibercrew with materials to arrive and begin restoration works.

  • Wednesday 20th, July 2022

    FR: Paris Backbone link between Paris and Frankfurt datacenters down

    At this moment we are experiencing problems with: Backbone link between Paris and Frankfurt datacenters

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are monitoring the situation and have reached out to our vendor for further investigation.

    Estimated time of repair: N/A

    Impact: Users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • IT: Milan Backbone links for our Bucharest datacenter is down

    At this moment we are experiencing problems with: Backbone link between our Milan and Bucharest datacenters down.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Milan and Bucharest datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident is resolved.

  • This incident was a backbone isolation rather than a full blackout of internet connectivity which included a fiber cut. We are contacting JTAC now for further investigation.

  • Tuesday 19th, July 2022

    US: Dallas Backbone link between our Dallas and Chicago datacenters down

    At this moment we are experiencing problems with: Backbone link between our Dallas and Chicago datacenters.

    The cause of the incident is currently: Unknown. We have reached out to our vendor for investigation.

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Chicago and Dallas datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • NL: Heerlen Smartdc Heerlen- Degraded cooling capacity

    At this moment we are experiencing problems with: Degraded cooling capacity.

    The cause of the incident is currently: Known.

    We have taken the following actions to resolve the incident: We have identified the cause and looking into a quick resolution to resolve the incident.

    Estimated time of repair: Unknown.

    Impact: Due to degraded cooling capacity, temperatures are rising. Colocation customers will see higher temperatures than usual.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Our datacenter engineers report that the issue has been resolved and temperatures are back to normal levels.

  • The temperatures are steadily going down at the moment. We will continue monitoring the situation.

  • All cooling units are back up and running. We will monitor the situation.

  • The ETA of the engineer is 17:15 UTC.

  • Our cooler vendor is sending a mechanic to further investigate the cooling units. No ETA.

  • Our efforts to get additional temporary cooling capacity are still underway.

  • Current plan of action is to utilize water cooling to cool down the compressors and restore them to a operational state. Our engineers are working hard to put this solution in operation.

  • We have a engineer on-site and additional staff in on the way to the Heerlen datacenter. The current issue is with the compressors that are overheating due to the outside temperatures. Datacenter staff are looking for alternative solutions to keep the compressors cool.

  • Monday 18th, July 2022

    FR: Paris Backbone link between our Paris and Rotterdam datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Paris and Rotterdam datacenters*.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown

    Impact: Due to the current incident on our backbone link between our Paris and Rotterdam datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This was due to a vendor maintenance that got extended. This incident has been resolved.

  • The link is stable. awaiting hands-off from vendor.

  • UAE: Dubai Backbone link between our Dubai and Saint Denis datacenters down.

    At this moment we are experiencing problems with: Backbone link between our Dubai and Saint Denis datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Dubai and Saint Denis datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • Sunday 17th, July 2022

    No incidents reported

    Saturday 16th, July 2022

    FR: Paris Backbone link between our Paris and Singapore datacenters down

    At this moment we are experiencing problems with: Backbone link between our Paris and Singapore datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Paris and Singapore datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • The link has been back online since 10:15 UTC, but we have not yet received hands off from our vendor.

  • Friday 15th, July 2022

    DE: Frankfurt Backbone link between Paris and Frankfurt datacenters down

    At this moment we are experiencing problems with: Backbone link between Paris and Frankfurt datacenters

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are monitoring the situation and have reached out to our vendor for further investigation.

    Estimated time of repair: N/A

    Impact: Users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The link is stable.

  • US: Newark Backbone link between our Newark and Montreal datacenters down

    At this moment we are experiencing problems with: Backbone link between our Newark and Montreal datacenters.

    The cause of the incident is currently: Unknown.

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Newark and Montreal datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved

  • RO: Bucharest Backbone link between our Budapest and Bucharest datacenters down

    At this moment we are experiencing problems with: Backbone link between our Budapest and Bucharest datacenters.

    The cause of the incident is currently: Known, fiber cut

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: ETR 5 hours

    Impact: Due to the current incident on our backbone link between our Budapest and Bucharest datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Two fibercuts were repaired, this incident has been resolved.

  • Our network vendor identified the issue being a fiber cut and have a repair crew on-site which started restoration work. ETR is 5 hours.