Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Network Maintenance] Router Software Update - Montreuil - December 11, 2025

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Montreuil datacenter. The network maintenance has been scheduled for December 11, 2025.

Location: Montreuil, France

Schedule: Start time: December 11, 2025, 00:00 UTC End time: December 11, 2025, 05:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our router(s) to improve quality and ensure long-term reliability.

Expected impact: Reduced redundancy: There will be reduced redundancy during the maintenance window; routers will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: Support You can find maintenance updates and the current situation at i3D.net - Status

[Network Maintenance] Aggregation Switch Software Update - Newark – January 6, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Newark datacenter. The network maintenance has been scheduled for January 6, 2026.

Location: Newark, America

Schedule: Start time: January 6, 2026, 09:00 UTC End time: January 6, 2026, 13:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to address difference in configuration behavior in newer software releases. This will prevent potential issues and ensure we can maintain stability.

Expected impact: Reduced Redundancy: As the activity will be executed by one aggregation switch at a time, there is no impact expected. During this maintenance there will be reduced redundancy.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: Support You can find maintenance updates and the current situation at i3D.net - Status

[Network Maintenance] Aggregation Switch Software Update - Newark – January 7, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Newark datacenter. The network maintenance has been scheduled for January 7, 2026.

Location: Newark, United States

Schedule: Start time: January 7, 2026, 09:00 UTC End time: January 7, 2026, 13:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to address difference in configuration behavior in newer software releases. This will prevent potential issues and ensure we can maintain stability.

Expected impact: Reduced Redundancy: As the activity will be executed by one aggregation switch at a time, there is no impact expected. During this maintenance there will be reduced redundancy.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: Support You can find maintenance updates and the current situation at i3D.net - Status

Vendor Cooling Maintenance – Rotterdam – January 19th, 2026

Dear Client,

We would like to notify you of upcoming emergency cooling maintenance activities that will affect services in our Rotterdam datacenter. The emergency cooling maintenance has been scheduled for January 19, 2026 through January 22, 2026.

Location: Rotterdam, Netherlands

Schedule: Start time: January 19, 2026, 7:00 UTC End time: January 22, 2026, 16:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing a cooling maintenance on our two cooling pumps of both A and B line to ensure continued performance, efficiency, and reliability of the system. We will adjust the start-up procedure so that both pumps start simultaneously

Expected impact: During the maintenance window the redundancy of the cooling system will be reduced

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: Support You can find maintenance updates and the current situation at i3D.net - Status

Past Incidents

Wednesday 29th, March 2023

DE: Frankfurt Frankfurt Datacenter PFE issues

We are currently experiencing issues with our PFE in our Frankfurt datacenter that is affecting traffic in the area.

  • The PFE issue has been resolved by draining, restart, and undrain the ports on FPC0. We have verified traffic returned to normal and have been stable for hours since then.

  • Tuesday 28th, March 2023

    No incidents reported

    Monday 27th, March 2023

    HU: Budapest Backbone link between our Bucharest and Budapest datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Bucharest and Budapest datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Bucharest and Budapest datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Fiber cut has been repaired and vendor is hands off resolving this incident.

  • DK: Copenhagen Backbone link between our Copenhagen and Amsterdam datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Copenhagen and Amsterdam datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates. our vendor is currently planning an emergency maintenance to fix the issues.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Copenhagen and Amsterdam datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident is resolved.

  • US: Ashburn Backbone link between our Ashburn and Newark datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Ashburn and Newark datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Ashburn and Newark datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident is resolved

  • Sunday 26th, March 2023

    No incidents reported

    Saturday 25th, March 2023

    No incidents reported

    Friday 24th, March 2023

    No incidents reported

    Thursday 23rd, March 2023

    IT: Milan Backbone link between our Milan and Bucharest datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Milan and Bucharest datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Milan and Bucharest datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • We have received a hands-off from our vendor

  • Our link has been restored. We are monitoring this link until we receive a hands-off from our vendor.

  • NL: Amsterdam Backbone link between our Amsterdam and Copenhagen datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Amsterdam and Copenhagen datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Amsterdam and Copenhagen datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Link remained stable

  • DK: Copenhagen Backbone link between our Copenhagen and Stockholm datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Copenhagen and Stockholm datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Copenhagen and Stockholm datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Our link has remained stable.

  • The link has been restored. We are still monitoring this link

  • SA: Johannesburg Network incident Johannesburg

    At this moment, we are experiencing problems with: Network in our Johannesburg Datacenter

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: Our engineers are working on resolving this issue. Follow the updates to this incident for more information.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our network in our Johannesburg Datacenter, users may experience loss of service.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. We experienced a crashing switch which restored. We are in contact with hardware vendor, reported this incident and provided logs to prevent this in the future.

  • NL: Amsterdam Backbone link between our Amsterdam and Montréal datacenters down

    At this moment we are experiencing problems with: Backbone link between our Amsterdam and Montréal datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Amsterdam and Montréal datacenters, we currently have reduced redundancy and possibly a slightly increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The link has remained stable.

  • The link has stabilized. We are still monitoring this link.

  • Wednesday 22nd, March 2023

    NL: Rotterdam Networkswitch incident Rotterdam - Suite 23 Rack 37

    At this moment we are experiencing problems with: One of our switches in Suite 23 Rack 37

    The cause of the incident is currently: Unknown.

    We have taken the following actions to resolve the incident: We are currently investigating the root cause of this incident

    Estimated time of repair: Unknown.

    Impact: Customers connected to this switch can experience service interruptions

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. Connectivity is back up and running stable since 08:38 CET / 07:38 UTC