Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Infrastructure Maintenance] Cooling Maintenance - Heerlen – March 23, 2026

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Heerlen datacenter. The cooling maintenance has been scheduled for March 23, 2026.

Location:

Heerlen, The Netherlands

Schedule:

Start time: March 23, 2026, 07:00 UTC

End time: March 23, 2026, 16:00 UTC

Planned impact: Reduced redundancy (see below for details)

Reason for Maintenance:

We will perform preventive maintenance on the cooling systems to ensure continued reliability and safe operation.

Expected Impact: During the maintenance the cooling units will be maintained one by one. Cooling will remain available, but redundancy will be temporarily reduced while the work is carried out.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Switch Software Upgrade - Ashburn - March 30, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Ashburn datacenter. The network maintenance has been scheduled for March 30, 2026.

Location: Ashburn, United States

Schedule: Start time: March 30, 2026, 08:00 UTC End time: March 30, 2026, 10:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to perform required software upgrades. This software upgrade will enhance system reliability and ensure consistent performance moving forward.

Expected impact: Reduced Redundancy: During this maintenance there will be reduced redundancy while one aggregation switch is maintained at a time.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Busbar Replacement - Rotterdam – March 31, 2026

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for March 31, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: March 31, 2026, 05:00 UTC End time: March 31, 2026, 16:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to address a faulty busbar. This critical replacement will enhance system reliability and ensure consistent performance moving forward.

Expected impact: Reduced redundancy: No impact expected but there will be no UPS backup. To ensure there is no impact we will run the generators in sync with the grid.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Router Software Upgrade - Oslo - April 1, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Oslo datacenter. The network maintenance has been scheduled for April 1, 2026.

Location: Oslo, Norway

Schedule: Start time: April 1, 2026, 04:00 UTC End time: April 1, 2026, 07:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our router(s) to improve quality and ensure long-term reliability.

Expected impact: No Impact: No impact is expected for this maintenance, as the traffic will be routed via alternate paths.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Dark-site test - Rotterdam – April 7, 2026

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The generator maintenance has been scheduled for April 7, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: April 7, 2026, 06:00 UTC End time: April 7, 2026, 09:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance: To ensure the proper functioning of our power infrastructure at our Rotterdam facility in the event of a power outage, our generators will undergo testing. We will simulate a real power outage by switching off power to our phase monitoring systems.

Expected impact: The lighting will briefly blink and there will be a short interruption on the B-feed during the switchover to the emergency power. If all systems function as expected, we will switch back when possible without extra interruption.

Reduced redundancy: As the generator control systems are switched to maintenance mode during the test run, auxiliary power redundancy is reduced during the maintenance window.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

Past Incidents

Thursday 25th, March 2021

No incidents reported

Wednesday 24th, March 2021

US: Ashburn Ashburn performance issues

At this moment we are experiencing problems with: A loss of services in the Ashburn region.

The cause of the incident is currently: unknown

Estimated time of repair: unknown

Impact: Loss of services

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This issue has been resolved.

  • Services should slowly be recovering.

  • US: Ashburn Network Event In Ashburn Datacenter

    At this moment we are experiencing problems with: A switch failure causing network disruptions in the Ashburn region.

    The cause of the incident is currently: Known

    We have taken the following actions to resolve the incident: We are working to reboot the switch and normalize traffic.

    Estimated time of repair: N/A

    Impact: Traffic in the region may be experiencing connectivity issues.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The switch has been rebooted. We are closely monitoring the situation. Services remain at-risk.

  • The switch experienced another failure. We are working to resolve the issue as soon as possible.

  • A switch failure caused a disruption in regional traffic. This incident has been resolved.

  • Tuesday 23rd, March 2021

    No incidents reported

    Monday 22nd, March 2021

    No incidents reported

    Sunday 21st, March 2021

    No incidents reported

    Saturday 20th, March 2021

    US: Los Angeles Backbone link between our Los Angeles and Dallas datacenters down

    At this moment we are experiencing problems with: Backbone link between our Los Angeles and Dallas datacenters down.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Los Angeles and Dallas datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This issue is resolved.

  • Backbone link between our Moscow and Copenhagen datacenters down

    At this moment we are experiencing problems with: Backbone link between our Moscow and Copenhagen datacenters down.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Moscow and Copenhagen datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This issue is resolved

  • The link is backup. However, we observe that the optical levels are unsatisfactory and several decibels worse than before the accident.

  • The technical team is on the scene and preparatory work is underway at the moment. However, they are having difficulties. ETR is unknown

  • An accident response team arrived on scene. ETR 18:00 UTC+3

  • Our vendor identified the cause of the incident. A technical team is dispatched. ETA is estimated at 14:00UTC+3

  • Friday 19th, March 2021

    NL: Rotterdam B-feed of Suite 07 and Suite 08 in our Rotterdam datacenter is experiencing an outage

    At this moment we are experiencing problems with: Suite 07 and Suite 08 are currently impacted due to an incident on one of the phases of the B-feed. As a result, some of the customers connected to the B-feed may have impact at this moment. In order to resolve this incident, emergency maintenance has to be performed on the B-feed.

    The cause of the incident is currently: known

    Estimated time of repair: 15 minutes

    Impact: Some of the customers connected to the B-feed may lose connection to their services

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The maintenance was completed at 12:02 UTC / 13:02 CET. All phases of the B-feed are back online and no further impact is expected. If you still experience issues, please get in contact with us!