Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Cooling Maintenance] Cooling Maintenance - Rotterdam – September 7 to October 7, 2026 - MCOM-454

Dear Client,

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The maintenance will take place on multiple dates between September 7 and October 7, 2026, as outlined below.

Location: Rotterdam, The Netherlands

Schedule:

Date

Maintenance window

September 7, 2026

05:00–14:00 UTC

September 9, 2026

05:00–14:00 UTC

September 11, 2026

05:00–14:00 UTC

September 14, 2026

05:00–14:00 UTC

September 16, 2026

05:00–14:00 UTC

September 18, 2026

05:00–14:00 UTC

September 23, 2026

05:00–14:00 UTC

September 25, 2026

05:00–14:00 UTC

September 28, 2026

05:00–14:00 UTC

September 30, 2026

05:00–14:00 UTC

October 2, 2026

05:00–14:00 UTC

October 5, 2026

05:00–14:00 UTC

October 7, 2026

05:00–14:00 UTC

Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing maintenance on our Stulz cooling units to support continued reliability and stability.

Expected impact: Reduced cooling redundancy: No impact is expected to services, but cooling redundancy will be reduced while the cooling units are being serviced. Minor temperature fluctuations may occur during the maintenance activities.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Aggregation Switch Upgrade - Stockholm - September 8, 2026 - MCOM-456

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Stockholm datacenter. The network maintenance has been scheduled for September 8, 2026.

Location: Stockholm, Sweden

Schedule: Start time: September 8, 2026, 03:00 UTC End time: September 8, 2026, 07:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Singapore – Aggregation Switch Upgrade – September 22, 2026

We would like to inform you of an upcoming network maintenance being performed in our Singapore datacenter. This maintenance is scheduled for September 22, 2026.

Location: Singapore, Singapore

Schedule: Start Time: September 22, 2026 19:00 UTC End Time: September 22, 2026 21:30 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Singapore – Aggregation Switch Upgrade – September 24, 2026

We would like to inform you of an upcoming network maintenance being performed in our Singapore datacenter. This maintenance is scheduled for September 24, 2026.

Location: Singapore, Singapore

Schedule:

Start Time: September 24, 2026, 19:00 UTC End Time: September 24, 2026, 21:30 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

Past Incidents

Wednesday 9th, June 2021

No incidents reported

Tuesday 8th, June 2021

US: Dallas Backbone link between our Dallas and Chicago datacenters down

At this moment we are experiencing problems with: Backbone link between our Dallas and Chicago datacenters.

The cause of the incident is currently: Unknown

We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

Estimated time of repair: No ETR available at this time.

Impact: Due to the current incident on our backbone link between our Dallas and Chicago datacenters, users between these and surrounding regions may experience increased latency.

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • All issues are resolved

  • This issue appears to have been resolved, however we are waiting for confirmation from the vendor.

  • US: Atlanta Backbone link between Dallas and Atlanta is down

    At this moment we are experiencing problems with: Backbone link between our Dallas and Atlanta datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Dallas and Atlanta datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • All previous issues are resolved.

  • This issue appears to have been resolved, however we are waiting for confirmation from the vendor.

  • US: Newark Backbone link between our Newark and Ashburn datacenters down

    At this moment we are experiencing problems with: Backbone link between our Newark and Ashburn datacenters down.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Newark and Ashburn datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • The link is restored. We are watching the connection since we have not received an hands-off from out vendor.

  • This outage is due to a maintenance by our vendor. Maintenance window is scheduled to end on June 08, 09:00 UTC.

  • Monday 7th, June 2021

    US: Los Angeles Backbone link between our Los Angeles and Dallas datacenters down

    At this moment we are experiencing problems with: Backbone link between our Los Angeles and Dallas datacenters down.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Los Angeles and Dallas datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The incident is resolved

  • Sunday 6th, June 2021

    No incidents reported

    Saturday 5th, June 2021

    No incidents reported

    Friday 4th, June 2021

    No incidents reported

    Thursday 3rd, June 2021

    No incidents reported

    Wednesday 2nd, June 2021

    UAE: Dubai Network Event in Dubai Datacenter

    At this moment we are experiencing problems with: Network incident Dubai datacenter

    The cause of the incident is currently: unknown

    Estimated time of repair: unknown

    Impact: Connectloss for end users in the dubai area. The connection is slowly recovering

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The issue is resolved