i3Dnet - [Network Maintenance] Aggregation Switch Upgrade - Stockholm – October 7, 2026 - MCOM-465 – Maintenance details

OCT7

[Network Maintenance] Aggregation Switch Upgrade - Stockholm – October 7, 2026 - MCOM-465

PlannedOctober 07, 2026 at 07:00 – 11:00UTC

Affects

Datacenters

Under maintenance from 7:00 AM to 12:00 AM

Stockholm - sesto2

Under maintenance from 7:00 AM to 12:00 AM

  • Planned
    September 16, 2026 at 22:08UTC
    Planned
    September 16, 2026 at 22:08UTC

    We would like to notify you of upcoming network maintenance activities that will affect services in our Stockholm datacenter. The aggregation switch upgrade has been scheduled for October 7, 2026.

    Location
    Stockholm, Sweden

    Schedule
    Start time: October 7, 2026, 03:00 UTC
    End time: October 7, 2026, 07:00 UTC

    Reason for this maintenance
    We will be performing firmware upgrades on our aggregation switches to improve quality and ensure long-term reliability.

    Expected impact
    Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.