We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The generator maintenance has been scheduled for October 6, 2026.
Location
Rotterdam, The Netherlands
Schedule
Start time: October 6, 2026, 06:00 UTC
End time: October 6, 2026, 08:00 UTC
Reason for this maintenance
To ensure the proper functioning of our power infrastructure, we will perform an off-load generator test to ensure ongoing reliability and compliance.
Expected impact
No Impact: The generator tests will be done off-load, services will remain fully supported by both the grid and generators. Some noise from the generators can be heard when present in the datacenter.