i3Dnet - [Network Maintenance] Aggregation Switch Upgrade - Sao Paulo – October 8, 2026 - MCOM-475 – Maintenance details

OCT8

[Network Maintenance] Aggregation Switch Upgrade - Sao Paulo – October 8, 2026 - MCOM-475

PlannedOctober 08, 2026 at 12:00 – 16:00UTC

Affects

Datacenters

Under maintenance from 12:00 PM to 12:00 AM

São Paulo - brcoa1

Under maintenance from 12:00 PM to 12:00 AM

  • Planned
    September 20, 2026 at 03:32UTC
    Planned
    September 20, 2026 at 03:32UTC

    We would like to notify you of upcoming network maintenance activities that will affect services in our São Paulo datacenter. The network maintenance has been scheduled for October 8, 2026.

    Location
    São Paulo, Brazil

    Schedule
    Start time: October 8, 2026, 08:00 UTC
    End time: October 8, 2026, 12:00 UTC

    Reason for this maintenance
    We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

    Expected impact
    Reduced redundancy: No impact is expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.