i3Dnet - MCOM-503 [Cooling Maintenance] Cooling Maintenance - Rotterdam – November 9, 2026 – Maintenance details

NOV7

MCOM-503 [Cooling Maintenance] Cooling Maintenance - Rotterdam – November 9, 2026

PlannedNovember 07, 2026 at 08:00 – November 17, 2026 at 15:00UTC

Affects

Datacenters

Under maintenance from 8:00 AM to 12:00 AM

Rotterdam - nlrtm1

Under maintenance from 8:00 AM to 12:00 AM

  • PlannedOctober 16, 2026 at 09:37UTC

    Dear Client,

    We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The cooling maintenance has been scheduled for November 9, 2026.

    Location:
    Rotterdam, The Netherlands

    Schedule:
    Start time: November 9, 2026, 06:00 UTC
    End time: November 17, 2026, 16:00 UTC
    Planned impact: Reduced redundancy (see below for details)

    Reason for this maintenance:
    We will be performing maintenance on our cooling units.

    Expected impact:
    Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window. During the maintenance window a small temperature can occur.

    Support:
    Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/
    You can find maintenance updates and the current situation at https://status.i3d.net/