i3Dnet - MCOM-504 | [Power Maintenance] Generator Maintenance - Heerlen – November 12, 2026 – Maintenance details

NOV12

MCOM-504 | [Power Maintenance] Generator Maintenance - Heerlen – November 12, 2026

PlannedNovember 12, 2026 at 05:30 – 13:00UTC

Affects

Datacenters

Under maintenance from 5:30 AM to 12:00 AM

Heerlen - nlhen1

Under maintenance from 5:30 AM to 12:00 AM

  • PlannedOctober 16, 2026 at 10:03UTC

    Dear Client,

    We would like to notify you of upcoming generator maintenance activities that will affect services in our Heerlen datacenter. The generator maintenance has been scheduled for November 12, 2026.

    Location:
    Heerlen, The Netherlands

    Schedule:
    Start time: November 12, 2026, 06:30 UTC
    End time: November 12, 2026, 14:00 UTC
    Planned impact: Reduced redundancy (see below for details)

    Reason for this maintenance:
    To ensure the proper functioning of our power infrastructure, our generators will undergo a no-load test run.

    Reduced redundancy: As the generator control systems are switched to maintenance mode during the test run, auxiliary power redundancy is reduced during the maintenance window.

    Support:
    Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/
    You can find maintenance updates and the current situation at https://status.i3d.net/