Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Power Maintenance] Busbar Replacement - Rotterdam – March 31, 2026

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for March 31, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: March 31, 2026, 05:00 UTC End time: March 31, 2026, 16:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required to address a faulty busbar. This critical replacement will enhance system reliability and ensure consistent performance moving forward.

Expected impact: Reduced redundancy: No impact expected but there will be no UPS backup. To ensure there is no impact we will run the generators in sync with the grid.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Router Software Upgrade - Oslo - April 1, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Oslo datacenter. The network maintenance has been scheduled for April 1, 2026.

Location: Oslo, Norway

Schedule: Start time: April 1, 2026, 04:00 UTC End time: April 1, 2026, 07:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our router(s) to improve quality and ensure long-term reliability.

Expected impact: No Impact: No impact is expected for this maintenance, as the traffic will be routed via alternate paths.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Breaker Maintenance Powerhouse 1 - Rotterdam – April 29

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for April 29, 2026

Location: Rotterdam, The Netherlands Suite 2 A Feed Suite 19 A and A+ Feed Suite 34 A and A+ Feed

Schedule: Start time: April 29, 2026, 08:00 UTC End time: April 29, 2026, 12:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance: Mandatory maintenance to ensure the safety, reliability and correct operation of our main power infrastructure.

Expected impact: Reduced redundancy: During the maintenance window, one of the power feeds supplying Suite 2, 19 and 34 will be temporarily unavailable. Power will remain available through the remaining feed(s), but power redundancy will be reduced for approximately 4 hours.

Please note that devices with a single power supply (single PSU) or devices connected only to the A feed will experience a service interruption during this maintenance window. Devices with dual power supplies connected to separate feeds are expected to remain online.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: i3d.net/support

[Cooling Maintenance] Water Cooling Pump Maintenance - Rotterdam – May 4, 2026

Dear Client,

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The water cooling pump maintenance has been scheduled for May 4, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: May 4, 2026, 07:00 UTC End time: May 4, 2026, 15:30 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: Our vendor will be performing a maintenance on the water pumps in our Rotterdam datacenter.

Expected impact: No Impact: No impact is expected, as maintenance activities will be performed on each water pump individually, with the team waiting for each pump to return to operation before proceeding to the next.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Generator On-load Test - Rotterdam – May 5, 2026

Dear Client,

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for May 5, 2026

Location: Rotterdam, The Netherlands

Original window: Start time: May 5, 2026, 06:00 UTC End time: May 5, 2026, 09:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: To ensure the proper functioning of our power infrastructure, our generators will undergo an on-load test run.

Expected impact: No Impact: No impact is expected for this maintenance, as there is no outage for the power systems. Customers in the datacenter at the time of the maintenance can hear loud noises.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

Past Incidents

Wednesday 8th, July 2020

US: Dallas IBX Utility Disturbance - Customer Loads Transferred to Generator Power

At this moment we are experiencing problems with: Staff in Dallas reports that the site experienced a loss of utility power and customer loads have transferred to generator power. As of July 8th, 4:22(CDT)/ 9:22pm(UTC), customer loads remain stable.

The cause of the incident is currently: Unknown. Staff are currently investigating. We have been advised an update will be posted if any significant changes to status(currently stable).

We have taken the following actions to resolve the incident: Monitoring situation with IBX staff.

Estimated time of repair: Unknown

Impact: Situation is currently stable

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. All load is running on utility power again.

  • Tuesday 7th, July 2020

    No incidents reported

    Monday 6th, July 2020

    No incidents reported

    Sunday 5th, July 2020

    US: Chicago Backbone link between our Chicago and Newark datacenters

    At this moment we are experiencing problems with: Backbone link between our Chicago and Newark datacenters

    The cause of the incident is currently: Fiber cut caused by installation work for new utility poles.

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and have reached out to our vendor for more information.

    Estimated time of repair: Unknown

    Impact: Some users may experience higher latency when connecting to our Chicago datacenter.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The link is back up.

  • The fiber cut has been located. The repair crew is expected to get access to the fiber cut to start work on restoring the link at around 21:00 UTC.

  • Saturday 4th, July 2020

    No incidents reported

    Friday 3rd, July 2020

    No incidents reported

    Thursday 2nd, July 2020

    Website i3D.net i3D.net Website

    At this moment we are experiencing problems with: the i3D.net website

    The cause of the incident is currently: unknown

    We have taken the following actions to resolve the incident: under investigation

    Estimated time of repair: unknown

    Impact: the i3D.net website is currently (partially) affected.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved, our website is fully operational again.

  • The cause of this incident has been found and a temporary fix has been implemented. We are working hard on a permanent solution.

  • Website Smartdc.net Smartdc Website

    At this moment we are experiencing problems with: the Smartdc website

    The cause of the incident is currently: unknown

    We have taken the following actions to resolve the incident: under investigation

    Estimated time of repair: unknown

    Impact: the Smartdc website is currently (partially) affected.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved, our website is fully operational again.

  • The cause of this incident has been found and a temporary fix has been implemented. We are working hard on a permanent solution.

  • Wednesday 1st, July 2020

    US: Ashburn Backbone link between our Ashburn and Dallas datacenters

    At this moment we are experiencing problems with: Backbone link between our Ashburn and Dallas datacenters

    The cause of the incident is currently: Fiber cut caused by a boring rig along a highway in San Marcos

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and have reached out to our vendor for more information.

    Estimated time of repair: Unknown

    Impact: Some users may experience higher latency and/or packet loss on their connection to our Dallas, Chicago, Los Angeles and Ashburn facilities.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The fibercut has been fully restored.

  • The Backbone Link is serving traffic again, but work has not been completed. ETR still unavailable.

  • The fibercut has been located and construction crews have been dispatched for repairs. No ETR at this time.

  • Our vendor has confirmed the issue to be a fiber cut caused by a boring rig along a highway in San Marcos. Due to the loss of this connectivity we are forced to re-route traffic elsewhere which may cause packet loss and/or added latency for users that are connecting to one of our following facilities: Los Angeles, Ashburn, Dallas and Chicago.