Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Cooling Maintenance] Cooling Maintenance - Rotterdam – September 7 to October 7, 2026 - MCOM-454

Dear Client,

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The maintenance will take place on multiple dates between September 7 and October 7, 2026, as outlined below.

Location: Rotterdam, The Netherlands

Schedule:

Date

Maintenance window

September 7, 2026

05:00–14:00 UTC

September 9, 2026

05:00–14:00 UTC

September 11, 2026

05:00–14:00 UTC

September 14, 2026

05:00–14:00 UTC

September 16, 2026

05:00–14:00 UTC

September 18, 2026

05:00–14:00 UTC

September 23, 2026

05:00–14:00 UTC

September 25, 2026

05:00–14:00 UTC

September 28, 2026

05:00–14:00 UTC

September 30, 2026

05:00–14:00 UTC

October 2, 2026

05:00–14:00 UTC

October 5, 2026

05:00–14:00 UTC

October 7, 2026

05:00–14:00 UTC

Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing maintenance on our Stulz cooling units to support continued reliability and stability.

Expected impact: Reduced cooling redundancy: No impact is expected to services, but cooling redundancy will be reduced while the cooling units are being serviced. Minor temperature fluctuations may occur during the maintenance activities.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Aggregation Switch Upgrade - Stockholm - September 8, 2026 - MCOM-456

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Stockholm datacenter. The network maintenance has been scheduled for September 8, 2026.

Location: Stockholm, Sweden

Schedule: Start time: September 8, 2026, 03:00 UTC End time: September 8, 2026, 07:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

MCOM-471 [Network Maintenance] Rotterdam – Aggregation Switch Upgrade – October 8, 2026

We would like to inform you of an upcoming network maintenance being performed in our Rotterdam datacenter. This maintenance is scheduled for October 8, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start Time: October 8, 2026, 03:00 UTC End Time: October 8, 2026, 07:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact is expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Singapore – Aggregation Switch Upgrade – September 22, 2026

We would like to inform you of an upcoming network maintenance being performed in our Singapore datacenter. This maintenance is scheduled for September 22, 2026.

Location: Singapore, Singapore

Schedule: Start Time: September 22, 2026 19:00 UTC End Time: September 22, 2026 21:30 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Singapore – Aggregation Switch Upgrade – September 24, 2026

We would like to inform you of an upcoming network maintenance being performed in our Singapore datacenter. This maintenance is scheduled for September 24, 2026.

Location: Singapore, Singapore

Schedule:

Start Time: September 24, 2026, 19:00 UTC End Time: September 24, 2026, 21:30 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Router Software Upgrade - Asia - September 28, 2026 - MCOM-466

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in datacenters across multiple locations in Asia. The network maintenance has been scheduled for September 28, 2026.

Locations: Fujairah, United Arab Emirates Hong Kong Shangai, China Singapore Tokyo, Japan

Schedule: Start time: September 28, 2026, 22:00 UTC End time: September 29, 2026, 02:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our router(s) to improve quality and ensure long-term reliability.

Expected impact: No Impact: We will do one router at a time and no impact is expected for dual or single homed customers. If any issues arise during deployment, there might be slight degradation for a few seconds.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

MCOM-468 | Planned Maintenance – Aggregation switches – Los Angeles, September 30, 2026

Dear Customer, We would like to inform you that we have scheduled maintenance activities.

Location: Los Angeles, United States

Schedule: Date: September 30, 2026 Start time: 08:00 UTC End time: 12:00 UTC Impact: Reduced redundancy

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switches to improve quality and ensure long-term reliability.

Expected impact: No impact expected, but there will be reduced redundancy during the maintenance window; aggregation switches will be upgraded one at a time to ensure minimum impact.

Contact: Our Live Operations team will be available for questions during the maintenance. More details about how you can contact our Live Operations team can be found here: https://i3d.net/support/

MCOM-469 | Planned Maintenance – Aggregation switches – Los Angeles, October 01, 2026

Dear Customer, We would like to inform you that we have scheduled maintenance activities.

Location: Los Angeles, United States

Schedule: Date: October 01, 2026 Start time: 08:00 UTC End time: 12:00 UTC Impact: Reduced redundancy

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switches to improve quality and ensure long-term reliability.

Expected impact: No impact expected, but there will be reduced redundancy during the maintenance window; aggregation switches will be upgraded one at a time to ensure minimum impact.

Contact: Our Live Operations team will be available for questions during the maintenance. More details about how you can contact our Live Operations team can be found here: https://i3d.net/support/

MCOM-470 | Planned Maintenance – Aggregation switches – Los Angeles, October 05, 2026

Dear Customer, We would like to inform you that we have scheduled maintenance activities.

Location: Los Angeles, United States

Schedule: Date: October 05, 2026 Start time: 08:00 UTC End time: 12:00 UTC Impact: Reduced redundancy

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switches to improve quality and ensure long-term reliability.

Expected impact: No impact expected, but there will be reduced redundancy during the maintenance window; aggregation switches will be upgraded one at a time to ensure minimum impact.

Contact: Our Live Operations team will be available for questions during the maintenance. More details about how you can contact our Live Operations team can be found here: https://i3d.net/support/

Global – Scheduled Infrastructure Migration – October 5th, 2026

We would like to inform you of an upcoming maintenance being performed globally. This maintenance is scheduled for October 5th, 2026

Location: Global

Schedule: Start Time: October 5th, 2026, 08:00 UTC End Time: October 7th, 2026, 14:00 UTC Planned impact: Reduced Redundancy (See below for details)

Reason for this maintenance: As we will be deprecating CDNv1 soon, we will be performing migrations from CDNv1 to CDNv2 for customers using ODP. This will improve quality and ensure long-term reliability.

Expected downtime/impact: To minimize any impact or issues we will be migrating one customer at a time, this will be a seamless transition with a small chance of brief cache cold-start. There will be a backup of the current configuration to roll back to if any issues arise.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

MCOM-476 [Power Maintenance] Rotterdam – Generator Maintenance – October 6, 2026

We would like to inform you of an upcoming power maintenance being performed in our Rotterdam datacenter. This maintenance is scheduled for October 6, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start Time: October 6, 2026, 06:00 UTC End Time: October 6, 2026, 08:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: To ensure the proper functioning of our power infrastructure, we will perform an off-load generator test to ensure ongoing reliability and compliance.

Expected downtime/impact: No Impact: The generator tests will be done off-load, services will remain fully supported by both the grid and generators. Some noise from the generators can be heard when present in the datacenter

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/
You can find maintenance updates and the current situation at https://status.i3d.net/

[Network Maintenance] Stockholm – Aggregation Switch Upgrade – October 7, 2026 - MCOM-465

We would like to inform you of an upcoming network maintenance being performed in our Stockholm datacenter. This maintenance is scheduled for October 7, 2026.

Location: Stockholm, Sweden

Schedule: Start Time: October 7, 2026, 03:00 UTC End Time: October 7, 2026, 07:00 UTC Planned impact: reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switches to improve quality and ensure long-term reliability.

Expected impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

MCOM-475 [Network Maintenance] Sao Paulo – Aggregation Switch Upgrade – October 8, 2026

We would like to inform you of an upcoming network maintenance being performed in our São Paulo datacenter. This maintenance is scheduled for October 8, 2026.

Location: São Paulo, Brazil

Schedule: Start Time: October 8, 2026, 08:00 UTC End Time: October 8, 2026, 12:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing firmware upgrades on our aggregation switch(es) to improve quality and ensure long-term reliability.

Expected downtime/impact: Reduced redundancy: No impact is expected, but there will be reduced redundancy during the maintenance window; aggregate switches will be upgraded one at a time to ensure minimum impact.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

Past Incidents

Wednesday 15th, July 2020

NL: Rotterdam Rotterdam, L2 colocation connectivity issues

At this moment we are experiencing problems with: Layer 2 colocation in our Rotterdam datacenter.

The cause of the incident is currently: Unknown. Staff are currently investigating.

We have taken the following actions to resolve the incident: Our network team is currently investigating.

Estimated time of repair: Unknown

Impact: Some L2 colocation users may experience higher latency and/or packet loss on their connection to our Rotterdam datacenter.

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. We will keep monitoring the situation for the upcoming few hours.

  • Our engineers have located where this issue is originating from and are working on a fix.

  • Tuesday 14th, July 2020

    No incidents reported

    Monday 13th, July 2020

    No incidents reported

    Sunday 12th, July 2020

    No incidents reported

    Saturday 11th, July 2020

    UAE: Dubai Link to Etisalat down

    At this moment we are experiencing problems with: Direct link to Etisalat

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We have opened up a ticket with Etisalat to have this investigated

    Estimated time of repair: Unknown

    Impact: All connectivity to and from Etisalat and our Dubai datacenter will see a significantly higher latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The link is back online, latency is back to normal for Etisalat users.

  • SG: Singapore Backbone link between our St. Denis and Singapore datacenters

    At this moment we are experiencing problems with: Backbone link between our St. Denis and Singapore datacenters

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and have reached out to our Vendor for more information.

    Estimated time of repair: Unknown

    Impact: Due to the current ongoing incident on our backbone link between our St. Denis and Singapore datacenters, our Singapore datacenter has now become isolated from the i3D.net network. This might increase latency for users to our Singapore datacenter.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Our backbone link is operational again.

  • Friday 10th, July 2020

    No incidents reported

    Thursday 9th, July 2020

    No incidents reported

    Wednesday 8th, July 2020

    US: Dallas IBX Utility Disturbance - Customer Loads Transferred to Generator Power

    At this moment we are experiencing problems with: Staff in Dallas reports that the site experienced a loss of utility power and customer loads have transferred to generator power. As of July 8th, 4:22(CDT)/ 9:22pm(UTC), customer loads remain stable.

    The cause of the incident is currently: Unknown. Staff are currently investigating. We have been advised an update will be posted if any significant changes to status(currently stable).

    We have taken the following actions to resolve the incident: Monitoring situation with IBX staff.

    Estimated time of repair: Unknown

    Impact: Situation is currently stable

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved. All load is running on utility power again.