Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Power Maintenance] Generator Maintenance - Rotterdam – June 9, 2026

We would like to notify you of upcoming power maintenance activities that will affect services in our Rotterdam datacenter. The power maintenance has been scheduled for June 9, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: June 9, 2026, 06:00 UTC End time: June 9, 2026, 09:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: We are conducting tests of our generators to ensure ongoing reliability and compliance.

Expected impact: The generator tests will be done off-load, services will remain fully supported by both the grid and generators. Some noise from the generators can be heard when present in the datacenter

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[API Maintenance] ONE API Migration - June 15, 2026

Dear Customer,

We would like to notify you of upcoming API maintenance activities that will affect the ONE API. The API maintenance has been scheduled for June 15, 2026.

Schedule: Start time: June 15, 2026, 09:00 UTC End time: June 15, 2026, 11:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance: We will be migrating and upgrading our ONE portal backend. This migration is part of our ongoing effort to enhance performance, scalability, and long-term reliability. Migrations and upgrades will be carried subsequently to minimise degradation in service and ensure a seamless transition.

Expected impact: Degradation: Our ONE API will remain available while migrating, but brief disruptions are expected. Customers using the ONE API will experience quick disconnects, and some active connections may have HTTP requests fail briefly. In the unlikely event of a critical failure we will roll back to the previous stable version.

Services impacted: One.i3d.net Api.i3d.net

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Cooling Maintenance] Cooling Maintenance - Rotterdam – June 22, 2026

Dear Client,

We would like to notify you of upcoming cooling maintenance activities that will affect services in our Rotterdam datacenter. The cooling maintenance has been scheduled for June 22, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: June 22, 2026, 05:00 UTC End time: July 10, 2026, 14:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: We will be performing a cooling maintenance on our cooling units to continue reliability and stability.

Expected impact:

Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window. There maybe some small temperature fluctuations as the units are being worked on.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

[Network Maintenance] Switch Software Upgrade - Rotterdam - June 24, 2026

Dear Client,

We would like to notify you of upcoming network maintenance activities that will affect services in our Rotterdam datacenter. The network maintenance has been scheduled for June 24, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: June 24, 2026, 03:00 UTC End time: June 24, 2026, 06:00 UTC Planned impact: Reduced redundancy (see below for details)

Reason for this maintenance: The maintenance is required in preparation for an upgrade to a new switch firmware. This will enhance system reliability and ensure consistent performance moving forward.

Expected impact: Reduced redundancy: No impact expected, but there will be reduced redundancy during the maintenance window.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/ You can find maintenance updates and the current situation at https://status.i3d.net/

[Power Maintenance] Yearly Generator Maintenance - Rotterdam – July 7, 2026

We would like to notify you of upcoming backup generator maintenance activities. This maintenance will not affect services in our Rotterdam datacenter. The maintenance has been scheduled for July 7 until July 17, 2026.

Location: Rotterdam, The Netherlands

Schedule: Start time: July 7, 2026, 05:00 UTC End time: July 17, 2026, 14:00 UTC Planned impact: No impact (see below for details)

Reason for this maintenance: To ensure the proper functioning of our power infrastructure, our backup generators will undergo preventative maintenance.

Expected impact: No Impact: No impact is expected for this maintenance, as regular power systems will not be touched. Customers in the datacenter at the time of the maintenance could hear loud noises.

Support: Our support department will be open during the maintenance. More details about how you can contact our support can be found here: https://i3d.net/support/

Past Incidents

Wednesday 18th, August 2021

Website i3D.net i3d.net and Smartdc.net website issues

At this moment we are experiencing problems with: the i3D.net and Smartdc.net websites.

The cause of the incident is currently: Unknown.

We have taken the following actions to resolve the incident: We are currently investigating this issue.

Estimated time of repair: Unknown.

Impact: https://www.i3d.net/ and https://www.smartdc.net websites are currently unavailable.

Support: Please contact support@i3d.net regarding any support issues.

  • This issue has been resolved and the websites are operating normally.

  • Tuesday 17th, August 2021

    No incidents reported

    Monday 16th, August 2021

    No incidents reported

    Sunday 15th, August 2021

    No incidents reported

    Saturday 14th, August 2021

    No incidents reported

    Friday 13th, August 2021

    No incidents reported

    Thursday 12th, August 2021

    US: Newark Backbone link between our Newark and Toronto datacenters down

    At this moment we are experiencing problems with: Backbone link between our Newark and Toronto datacenters.

    The cause of the incident is currently: Unknown. We have reached out to our vendor for investigation.

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: No ETR available at this time.

    Impact: Due to the current incident on our backbone link between our Newark and Toronto datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The incident has been resolved.

  • Our vendor reports a fiber cut has been identified and crews are working to restore the connection. No ETR provided at this time.

  • JP: Tokyo Backbone link between our Hong Kong and Tokyo datacenters down

    At this moment we are experiencing problems with: Backbone link between our Hong Kong and Tokyo datacenters.

    The cause of the incident is currently: Known, seacable fault.

    We have taken the following actions to resolve the incident: We have contacted our vendor to investigate this incident.

    Estimated time of repair: The current ETR is the 12th of September.

    Impact: Due to the current incident on our backbone link between our Hong Kong and Tokyo datacenters, users surrounding these datacenters may experience an increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This incident has been resolved.

  • A permit has been secured. The ETA of the ship to arrive at the cable ground is the 15th of September. Meanwhile we have another link fully operational, so there currently is no impact.