Some systems are experiencing issues

About This Site

Welcome to the status page of i3D.net. Any known issues affecting any of our services will be tracked on this page. Potential impact may vary from customer to customer depending on the systems or services impacted.

All times used on this page will be in the UTC timezone.

You can subscribe to receive an email as soon as a status update has been published. You may consult our Privacy Statement for more information on the processing of your personal data.

Please reach out to our support team through our website or support@i3d.net if you have any questions or need help.

We are also available 24/7 by phone on the following phone numbers:

+31 (0)10 890 00 70

1-800-482-6910

Maintenance
[Vendor Power Maintenance] Vendor Maintenance - Sydney – July 14-20, 2025

We would like to notify you of upcoming emergency vendor maintenance activities that will affect services in our Sydney datacenter. The emergency vendor maintenance has been scheduled to start on July 14, 2025 and finish on July 20, 2025.

Location: Sydney, Australia

Schedule: Start time: July 14, 2025, 21:00 UTC End time: July 20, 2025, 08:00 UTC Planned impact: Impact expected (see below for details)

Reason for this maintenance:

The vendor is implementing improvements to the datacenter power delivery, requiring both the A- and B-feeds to be temporarily disconnected.

Expected impact: Full downtime / reduced redundancy.

During this emergency vendor power maintenance, our vendor will disconnect either the A- or B-feeds during daily maintenance windows from 21:00 - 08:00 UTC on July 14 until July 20.

If your server is connected redundantly this means one of the connected PSUs will be disconnected during these windows (reduced redundancy).

If your server is connected to a single power feed, this means full downtime for the duration of the maintenance works.

[Cooling Maintenance] Rotterdam – Data Center Air Supply Temperature Change – July 21, 2025

We would like to inform you of an upcoming cooling maintenance being performed in our Rotterdam datacenter. This maintenance is scheduled for July 22nd, 2025.

Location:

Rotterdam, The Netherlands

Schedule:

Start Time: July 21, 2025, 06:00 UTC

End Time: August 21, 2025, 18:00 UTC

Planned downtime:

No downtime is expected

Reason for this maintenance:

As part of our ongoing commitment to energy efficiency and environmental responsibility we will begin increasing the air supply temperature in our server rooms from 22°C to 24°C. This adjustment is being made to improve the overall energy efficiency of our facility, to ensure we continue complying with European regulatory guidelines and to reduce the load on our cooling systems.

Expected downtime/impact:

No downtime is expected.

[Maintenance] 2025 Rotterdam Q3 quarterly on-load tests

Dear customer,

In the below overview you will find the date and time of our planned on-load tests in our  Smartdc Rotterdam datacenter for Q3 2025:

Location: Rotterdam, The Netherlands

On-load test Q3: Startdatum: 5 August 2025, 06:00 UTC Einddatum: 5 August 2025, 08:00 UTC

Expected downtime: None expected

Impact:  No impact expected

Reason for these maintenances: These on-load tests are routine and meant to test the back-up power systems of our Rotterdam facility. This is to ensure that everything remains fully operational in the event of a power outage in the facility.

Support: Our support department will be open during the maintenances. More details about how you can contact our support can be found on https://i3d.net/support/

Past Incidents

Saturday 10th, June 2023

SG: Singapore Backbone link between our Singapore and Mumbai datacenters down

At this moment, we are experiencing problems with: Backbone link between our Singapore and Mumbai datacenters.

**The cause of the incident is currently: Unknown

We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

Estimated time of repair: Unknown.

Impact: Due to the current incident on our backbone link between our Singapore and Mumbai datacenters, users between these and surrounding regions may experience increased latency.

Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Fiber cut repaired

  • US: Chicago Backbone link between our Toronto and Chicago datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Toronto and Chicago datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Our third-party provider has extended their maintenance.

    Impact: Due to the current incident on our backbone link between our Toronto and Chicago datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Maintenance has been completed and has remained stable since.

  • Friday 9th, June 2023

    No incidents reported

    Thursday 8th, June 2023

    US: Dallas Backbone link between our Dallas and Chicago datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Dallas and Chicago datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Dallas and Chicago datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Technicians have fixed the fiber cut and services are restored. This issue is resolved.

  • A fiber cut has been found. Repair efforts are ongoing.

  • Wednesday 7th, June 2023

    US: Ashburn Backbone link between our Toronto and Ashburn datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Toronto and Ashburn datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Toronto and Ashburn datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Link restored

  • A fiber fault has been identified in our third-party provider's network.

  • DE: Frankfurt Backbone link between our Frankfurt and Paris datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Frankfurt and Paris datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Frankfurt and Paris datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The link has been restored

  • Tuesday 6th, June 2023

    IN: Mumbai Backbone link between our Mumbai and Singapore datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Mumbai and Singapore datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Mumbai and Singapore datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • This link has remained stable since the initial flap. This issue is resolved.

  • US: Ashburn Backbone link between our Atlanta and Ashburn datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Atlanta and Ashburn datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Atlanta and Ashburn datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Our vendor's technicians were able to repair the faulty equipment and service has been restored. This incident is resolved.

  • Monday 5th, June 2023

    ES: Madrid Backbone link between our Madrid and Johannesburg datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Madrid and Johannesburg datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Madrid and Johannesburg datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • The dual fiber cut has been repaired and service is restored. The incident is resolved.

  • A fiber cut has been identified, a team is currently being assembled to repair the broken fiber.

  • Sunday 4th, June 2023

    No incidents reported

    Saturday 3rd, June 2023

    Website i3D.net i3D.net Website unreachable

    At this moment we are experiencing problems with: the i3D.net website

    The cause of the incident is currently: unknown

    We have taken the following actions to resolve the incident: under investigation

    Estimated time of repair: unknown

    Impact: the i3D.net website is currently (partially) affected.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

    Backbone link between our Stockholm and Saint Petersburg datacenters down

    At this moment, we are experiencing problems with: Backbone link between our Stockholm and Saint Petersburg datacenters.

    The cause of the incident is currently: Unknown

    We have taken the following actions to resolve the incident: We are currently monitoring the situation and are in touch with our vendor regarding status updates.

    Estimated time of repair: Unknown.

    Impact: Due to the current incident on our backbone link between our Stockholm and Saint Petersburg datacenters, users between these and surrounding regions may experience increased latency.

    Support: Our support department is available for more information and personal updates. New updates will be posted here. More details about how you can contact our support can be found here.

    Subscribe for the latest updates. You may consult our Privacy Statement for more information on the processing of your personal data.

  • Incident was caused by a maintenance on vendor partner's network which failed to notify due to human error.

  • Link has been re-established and remained up for over a hour. Waiting on Vendor to give the confirmation of the root cause to be resolved.